Purpose
Make corrections after the month has been submitted by reversing the process in the correct order.
Before You Start
Month must be in Submitted status.
Manager and HR involvement is required.
Steps
Request HR to Reopen Month.
Request manager to Reopen Week.
Go to Time Entries > My Timesheet.
Adjust entries.
Submit the week again.
Wait for approval.
Submit the month again.
Important Rules
Reopening only the week is not sufficient if month is closed.
The sequence must be reversed: Month → Week.
Changes are not valid until the month is resubmitted.
Common Issues
Issue: I reopened the week but still cannot submit changes
Likely cause: Month is still locked.
How to solve: Confirm HR reopened the month first.