Purpose

Make corrections after the month has been submitted by reversing the process in the correct order.


Before You Start

  • Month must be in Submitted status.

  • Manager and HR involvement is required.


Steps

  1. Request HR to Reopen Month.

  2. Request manager to Reopen Week.

  3. Go to Time Entries > My Timesheet.

  4. Adjust entries.

  5. Submit the week again.

  6. Wait for approval.

  7. Submit the month again.


Important Rules

  • Reopening only the week is not sufficient if month is closed.

  • The sequence must be reversed: Month → Week.

  • Changes are not valid until the month is resubmitted.


Common Issues

Issue: I reopened the week but still cannot submit changes
Likely cause: Month is still locked.
How to solve: Confirm HR reopened the month first.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article