Time Entries — How To: Correct Time Entries After Week Submission

Modified on Wed, 18 Feb at 4:32 PM

Purpose

Understand how to adjust time entries after week submission. The system requires reopening before editing.


Before You Start

  • Week must be in Submitted, Approved, or Rejected status.

  • If the month is already submitted, it must be reopened first.


Steps

  1. Contact your manager.

  2. Request Week Reopening.

  3. After reopening, access Time Entries > My Timesheet.

  4. Edit entries.

  5. Submit the week again.


If month was submitted:

  1. Request HR to reopen the month first.

  2. Then request manager to reopen week.


Important Rules

  • Reopening only the week is not enough if the month is submitted.

  • Reopen sequence must be reversed: Reopen Month → Reopen Week.


Common Issues

Issue: I reopened the week but still cannot edit
Likely cause: Month is still closed.
How to solve: Ask HR to reopen the month first.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article